Solar permitting — Buffalo County, Wisconsin
280 indexed meetings (13 energy-related), 1 known opposition group.
W WI agricultural; Alma area; Mississippi River bluffs add scenic sensitivity; local CUP. Permitting: Buffalo County: CUP in Agricultural/Industrial district for projects <100 MW.; 200-ft setback. Track record: no prior utility-scale…
Permitting process
Local permitting pathway
Buffalo County: CUP in Agricultural/Industrial district for projects <100 MW.
Setbacks & buffers
Wisconsin sets NO statewide numeric setback for utility-scale solar. A facility of 100 MW or greater needs a certificate of public convenience and necessity from the PSC (s. 196.491(3)(a)1.); below that threshold, PSC approval is generally required only for a public utility and does not address siting. Local restrictions are constrained by s. 66.0401(1m), which bars a political subdivision from restricting a solar energy system unless the restriction protects public health or safety, does not significantly increase cost or decrease efficiency, or allows a comparable alternative — and Ecker Brothers v. Calumet County, 2009 WI App 112, holds that this requires a case-by-case approach rather than a one-size-fits-all ordinance. In practice setbacks are set per project in local operating or joint development agreements — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.
Spacing requirements
None codified.
Size restrictions
None codified; managed via CUP/SUP conditions
Penalties & bonding
No penalties or adjustments. Standard CUP/SUP process.
State-level permits & approvals
PSC of Wisconsin has siting authority for wind/solar ≥100 MW (Wis. Stat. §196.491). Projects <100 MW: local CUP/SUP under county/town zoning governs. Local restrictions on wind systems must meet one of 3 conditions: (1) public health/safety; (2) not significantly increase cost/decrease efficiency; (3) allows comparable alternative. Local solar restrictions face similar reasonableness standard. No statewide preemption below 100 MW threshold — strong local control. MISO interconnection territory statewide.
Full records for this county are part of a SitePath subscription.
State policy & grid context
State RPS & clean energy policy
10% by 2015 (met, no update) | Act 141 (2005) | Wis. Stat. §196.378
State incentive programs
Wisconsin RPS: 10% renewable by 2015 (met — weakest in region). Focus on Energy program: commercial/industrial rebates for solar ($150-450/kW for ≤25 kW). Property tax exemption: Wis. Stat. §70.111(18) — solar systems exempt from property tax assessment. Sales tax exemption: Wis. Stat. §77.54(57m) — solar equipment purchases exempt. Wisconsin Green Energy program: voluntary renewable program through WPS, MGE, We Energies. Alliant WPL (WI) has deployed ~1,089 MW solar by 2024; Vista Sands (1,315 MW Portage Co.) approved June 2025 — largest WI solar project. Utility: We Energies (WEC) serves SE WI/Milwaukee; WPS (WEC) serves NE WI; Alliant Energy (WPL) serves central/southern WI; MGE serves Madison metro; Xcel NSPW serves far NW WI; Dairyland Power Coop and WPPI Energy serve rural areas.
Grid & interconnection
MISO / Dairyland Power Cooperative (DPC) zone
Full records for this county are part of a SitePath subscription.
Battery storage (BESS) P1 State-Default Permitting
No standalone county BESS ordinance confirmed.
BESS ordinances & bylaws
County-level battery-storage status, safety requirements, and projects — each linked to a primary source.
Community opposition P1 1 tracked
Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.
SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.
Subscriber intel Subscribers
Researched for this county and available with a subscription:
- 🔒Project track record
- 🔒Developer intelligence
- 🔒Governing board
Energy-related meetings & dockets P1
Halo color matches the energy category tagged on each meeting.
- 2026-05-18 OtherData Center
O'Connor supports the data center ordinance amendment
- 2026-05-18 OtherData Center
Data Center A. Data Centers will only be allowed in an industrial zoning district as a conditional use.
- 2026-05-01 OtherData Center
Data center project approved with noise level restrictions.
- 2026-05-01 OtherData Center
The Planning Commission approved a conditional use permit for Data Center A, allowing it to be built in an industrial zoning district.
- 2026-04-06 OtherSolar
Buffalo County is considering an amendment to its solar ordinance to add a decommissioning/demolition requirement for new solar systems.
- 2026-04-02 OtherSolar
Amendments were made to several ordinances, including the Comprehensive Zoning Ordinance, to add data centers to conditional use industrial zoning and clarify nonconforming lot use.
- 2026-03-23 OtherSolar
Review and potential amendment of the Buffalo County Solar Ordinance
- 2026-03-23 OtherSolar
Buffalo County Board of Supervisors adopted amendments to the Buffalo County Solar Ordinance.
- 2026-03-23 Zoning BoardData Center
The county discussed the definition of various structures, including data centers, day care facilities, and decks.
- 2026-03-23 OtherSolar
Buffalo County discussed an amendment to the 'Buffalo County Solar Ordinance' regarding decommissioning of new solar systems.
- 2026-03-13 OtherSolar
Buffalo County Board of Supervisors will consider adopting proposed amendments to the Buffalo County Solar Ordinance.
- 2026-03-13 OtherSolar
Review of GIS/LIO Report
- 2026-03-13 OtherSolar
Amendments were made to several ordinances, including the Comprehensive Zoning Ordinance, to add data centers to conditional use industrial zoning and clarify nonconforming lot use.
Full records for this county are part of a SitePath subscription.
State PSC dockets P1
No tracked activity yet — coverage expands weekly.
Local news P3
No tracked activity yet — coverage expands weekly.
Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.