Solar permitting — Whitman County, Washington

FIPS 53075

145 indexed meetings (34 energy-related), 1 news item, 5 known opposition groups.

D
Whitman County, WA
Risk score 55/100 · Full scorecard →
Compliance: HighNo local solar ordinanceTrajectory: StableSaturation: Low

Palouse wheat community identity and commissioner caution about ag land conversion drive moderate-to-elevated risk; WSU presence and good irradiance… Permitting: Whitman County: CUP in Agricultural zones. Political envi…

Key driver: Palouse wheat community identity and commissioner caution about ag land conversion drive moderate-to-elevated risk; WSU presence and good irradiance provide development opportunity.

Permitting process

Local permitting pathway

Whitman County: CUP in Agricultural zones; Zoning Adjustment Board and Board of County Commissioners; Pullman city processes residential/commercial separately.

Setbacks & buffers

No county-specific solar setbacks; standard agricultural setbacks apply.

Spacing requirements

None codified.

Size restrictions

None codified; managed via CUP/SUP conditions

Penalties & bonding

No penalties or adjustments. Standard CUP/SUP process.

State-level permits & approvals

Large facilities (≥350 MW): EFSEC exclusive jurisdiction. <350 MW: county CUP/SUP; no statewide preemption floor. SEPA review required. GMA energy siting required in comprehensive plans. SMA applies near shorelines. Critical Areas Ordinances: wetlands, fish habitat, flood zones require county CAO compliance. Ag land conversion: county-specific farmland protection policies apply.

🔒
Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% clean by 2045 | Clean Energy Transformation Act / SB 5116 (2019) | RCW 19.405

State incentive programs

Washington Clean Energy Transformation Act (CETA/SB 5116, 2019): IOUs carbon-neutral by 2030; 100% carbon-free by 2045. Net metering: ≤100 kW IOU customers under WUTC; PUDs set individual limits. RESIP: production incentives for ≤100 kW systems. Sales & use tax exemption (RCW 82.08.962). Property tax exemption (RCW 84.36.635). Community solar via PSE, SnoPUD, Tacoma Power, Clark Public Utilities, and most WA PUDs. PACE financing in participating counties. Federal ITC: 30% (IRA 2022); 10% low-income adder for qualifying projects.

Grid & interconnection

WECC / BPA Transmission — Pacific Power, Avista, and Whitman Electric Co-op service territory; Palouse grid

🔒
Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Battery storage (BESS) P1 State-Default Permitting

No confirmed county BESS ordinance.

Local BESS ordinances & bylaws

County-level battery-storage status, safety requirements, and projects — each linked to a primary source.

Community opposition P1 5 tracked

Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.

SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to view

Energy-related meetings & dockets P1

22 energy-related145 total in calendar17 bess · 3 solar · 2 data center

Halo color = sentiment of the relevant agenda excerpt: green positive, yellow neutral, red negative.

  • 2026-06-17 Planning Commission
    BESS

    Whitman County Planning Commission discussed development of a solar and battery energy storage ordinance.

  • 2026-06-17 Other
    BESS

    Planning Commission discussed a battery storage project and its feasibility in relation to local ordinance language.

  • 2026-06-15 County Board
    BESS

    Whitman County considered extending a moratorium on new solar and battery storage projects.

  • 2026-06-09 Other
    Solar

    A massive solar farm and wind turbine project are proposed for development on the Central Ferry hillside in Garfield County.

  • 2026-06-03 Planning Commission
    BESS

    Prior to issuance of any building permit or operation of a Battery Energy Storage System (BESS), the applicant shall prepare and submit a site­ specific Emergency Response and Emergency Operations Plan.

  • 2026-06-03 Other
    BESS

    Continuation of draft language for solar and battery energy storage ordinances

  • 2026-06-01 County Board
    Solar

    Whitman County Commissioners discussed a moratorium extension for battery and solar projects.

  • 2026-05-20 Planning Commission
    BESS

    The Planning Commission voted to deny a special-use permit application for a 150 MW solar farm

  • 2026-05-20 Other
    BESS

    The Planning Commission voted to deny a special-use permit application for a 150 MW solar farm

  • 2026-05-06 Planning Commission
    BESS

    The Planning Commission approved the continuance of updating the Critical Areas Ordinance and the creation of ordinances for solar and battery storage.

  • 2026-05-06 Other
    Solar

    The Planning Commission voted to deny a special-use permit application for a 150 MW solar farm due to limited area zones.

  • 2026-04-15 Planning Commission
    BESS

    The Planning Commission approved the proposed changes to the Critical Areas Ordinance, allowing for the creation of solar and battery storage ordinances.

  • 2026-04-01 Planning Commission
    BESS

    The Planning Commission approved a special-use permit application for a 150 MW solar farm.

  • 2026-03-18 Planning Commission
    BESS

    The Planning Commission approved a special-use permit application for a 150 MW solar farm.

  • 2026-03-18 Other
    Data Center

    The Planning Commission voted to approve a proposal to build a data center in a previously designated area.

  • 2026-03-04 Planning Commission
    BESS

    The Planning Commission approved a special-use permit application for a 150 MW solar farm and voted to deny it.

  • 2026-03-04 Other
    BESS

    The Critical Areas Ordinance will be updated to include solar and battery storage projects.

  • 2026-02-04 Planning Commission
    BESS

    The Planning Commission will discuss and vote on a Critical Areas Ordinance update that includes creating a solar and battery storage ordinance.

  • 2026-02-04 Other
    BESS

    Planning Commission approved the solar and battery storage ordinance

🔒
19 more energy-related meetings

Full records for this county are part of a SitePath subscription.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Sentiment rollup P2

No sentiment rollup yet (requires meeting transcripts to be processed).

Local news P3

Explore all 3,143 counties on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Washington counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS; sentiment derived from public meeting transcripts. Last refreshed 2026-08-21. See the county risk scorecard or the full Washington permitting index.