Solar permitting — Mecklenburg County, Virginia

FIPS 51117

On file: public meetings, local news, known opposition groups.

D
Mecklenburg County, VA
Risk score 60/100 · Full scorecard →
Compliance: Very HighTrajectory: WorseningSaturation: Very High

Board of Supervisors voted unanimously April 14 2025 to REMOVE utility-scale solar as a permitted use (revised Article 20); all-Republican board (Fisher, Graham, Massengill, McGhee, Clanton). NOTE: Virginia HB 711/SB 347 (eff. July 1, 2…

Key driver: Article 20 (Apr 2025) removes utility-scale as permitted use — functional ban. CRITICAL: HB 711/SB 347 — if signed, Mecklenburg's ban becomes illegal and must be repealed or amended to allow SE applications. Risk trajectory shifts from Worsening toward Stable once legislation signed, but board hostility remains; denials via SE process still possible.

Permitting process

Local permitting pathway

Utility-scale solar removed (no longer allowed as new land use); small/medium-scale allowed with limits in specified districts.

Setbacks & buffers

150 ft from property lines

Spacing requirements

Ordinance amendment packet references distance controls relative to other solar facilities (applied to remaining categories).

Size restrictions

Utility-scale removed; remaining categories include acreage limits (see amendment packet).

Penalties & bonding

Total penalty: +5 (Denial +5)

State-level permits & approvals

Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.

Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5

State incentive programs

Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.

Grid & interconnection

PJM / Dominion Energy Virginia (DEV) transmission zone

Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Battery storage (BESS) P1 State-Default Permitting

Standalone BESS (not co-located with approved solar): still requires county SE/SUP and host siting agreement

Local BESS ordinances & bylaws

County-level battery-storage status, safety requirements, and projects — each linked to a primary source.

Community opposition P1

Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.

SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to view

Energy-related meetings & dockets P1

solar · data center · bess

Halo color matches the energy category tagged on each meeting.

  • 2025-03-27 Planning Commission
    Solar

    Proposed amendments to Mecklenburg County Zoning Ordinance to remove utility-scale solar facilities as a permitted use

  • 2023-09-11 County Board
    Solar

    Board of Supervisors discussed a financial agreement for the Finneywood Solar Project with Dominion Energy Virginia.

  • 2023-05-08 County Board
    Solar

    The Planning Commission must review any proposed solar project to ensure it aligns with the County's Comprehensive Plan.

  • 2021-07-12 County Board
    Solar

    Commercial solar permit applications will require a stated completion date and may incur additional fees for delays.

  • Other
    Solar

    The Mecklenburg County Board of Supervisors voted to deny a special-use permit application for a 150 MW solar farm proposed by Antlers Road Solar, LLC.

  • Zoning Board
    Solar

    The Planning Commission voted to approve a special-use permit application for a 150 MW solar farm

  • County Board
    Solar

    Planning Commission extended review of Antlers Road Solar Project

  • Planning Commission
    Solar

    Mecklenburg County Planning Commission approved a public hearing for a solar project with no changes

  • County Board
    Solar

    The Grasshopper Solar Project is complete, but concerns remain about run-off into Butcher's Creek.

  • Other
    Solar

    4 13-5 Off-Street Lo ading Requirements 14 TOWERS AND ANT ENNAS 141 14-1 Definitions 14-2 Uses 14-3 Applicability 14-4 Guidelines and Requirements 14-5 Federal Requirements 14-6 Building Codes 14-7 Information Required 14-8 Factors for Spec

More energy-related meetings

Full records for this county are part of a SitePath subscription.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Local news P3

Explore every US county on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Virginia counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS. Last refreshed 2026-10-11. See the county risk scorecard or the full Virginia permitting index.