Solar permitting — Hanover County, Virginia
On file: public meetings, local news, known opposition groups.
Growing opposition; ordinance tightened post-2022; high community organized resistance; worsening political trajectory. Permitting: A-1; 50-ft setback; application fee $1. Track record: denial on record — North Ann…
Permitting process
Local permitting pathway
A-1, Agricultural | SUP
Setbacks & buffers
Hanover County-specific SE/SUP conditions control — county-set setbacks vary from 50 ft (rural) to 300+ ft (residential adjacent). Verify current Hanover County zoning ordinance for adopted local setback standards. — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.
Spacing requirements
Viewshed and scenic corridor protections emphasized.
Size restrictions
~150–300 ac typical via SUP
Penalties & bonding
Total penalty: +5 (Denial +5)
State-level permits & approvals
Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.
Full records for this county are part of a SitePath subscription.
State policy & grid context
State RPS & clean energy policy
100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5
State incentive programs
Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.
Grid & interconnection
PJM / Dominion Energy Virginia (DEV) transmission zone
Full records for this county are part of a SitePath subscription.
Battery storage (BESS) P1 CUP / SUP Required
SEPARATE BATTERY STORAGE ORDINANCE — Hanover County implemented a battery storage ordinance in 2023-2024 (concurrent with/following the solar ordinance)
Local BESS ordinances & bylaws
County-level battery-storage status, safety requirements, and projects — each linked to a primary source.
Community opposition P1
Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.
- r/nova on Reddit: Noise of Virginia data center drowns out neighborhood Data center
- r/Virginia on Reddit: Hanover County votes to deny 1,500-acre solar development Solar
- r/Virginia on Reddit: Most of Virginia restricts solar farms. Lawmakers want to change that. Data center
- Data centers approved, solar farms rejected: What is going on in rural Virginia? • Virginia Mercury Data center
- Community opposition to Tract Data Center data center Data center
- Community opposition to Hunter Hawking Data Center data center Data center
SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.
Subscriber intel Subscribers
Researched for this county and available with a subscription:
- Project track record
- Developer intelligence
- Governing board
Energy-related meetings & dockets P1
Halo color matches the energy category tagged on each meeting.
- 2026-06-10 Utility BoardData Center
Hanover County school officials are considering developing curriculum for workforce development in information technology and the trades.
- 2026-05-13 OtherData Center
The Hanover County Economic Development Authority approved a data center project with a proposed tax rate of 2.5%.
- 2026-04-03 OtherData Center
Morris, IL Page 2 Hanover County, VA Assumptions: Projected site and data center CAPEX Location Address Projected Capital Expenditures (over 20-years) Job Creation Real Property Personal Property (including refresh) Est.
- 2024-10-17 Planning CommissionData Center
The proposed zoning amendment would allow development of a data center campus (multiple buildings permitted within the development area) and 49 single-family detached homes.
- 2024-09-25 OtherSolar
(PUBLIC HEARING) Magisterial District: Cold Harbor CUP2024-00007, STRATA CLEAN ENERGY Requests a Conditional Use Permit in accordance with Section 26-20.39 of the Hanover County Zoning Ordinance to allow a principal utility -scale solar ene
- OtherData Center
The proposed zoning amendment would allow for the development of a data center and associated uses.
- OtherData Center
The Board approved a motion for County staff to research data centers and develop a policy/ordinance.
- OtherData Center
The Board approved a motion for County staff to research data centers and develop a policy/ordinance.
- OtherData Center
Hanover County Board of Supervisors launched public review of data center policy and tax rate
- OtherData Center
Hanover County Board of Supervisors launched public review of data center policy and tax rate
- OtherData Center
Hanover County discussed a data center project at the Mountain Road Technology Park
- OtherData Center
Hanover County, VA officials discussed a data center project with estimated capital expenditures of $9 billion and potential job creation.
- OtherData Center
The Board approved a motion for County staff to research data centers and develop a policy/ordinance.
- OtherBESS
Hanover County discussed the benefits of Battery Energy Storage Systems (BESS) for residents and businesses.
- OtherSolar
Building Inspections: Implemented a plan review and inspection program for residential energy efficiency 7,170 permits issued (up from 6,678 in FY23) $158.9M in permit fees, up slightly from $158.8M in FY23 General Services: Montpelier Recr
- OtherSolar
Planning Commission discussed a Conditional Use Permit for a solar power facility on approximately 955.21 acres.
- OtherData Center
Hanover County's Council reviewed data center and tax rate policy.
- OtherData Center
Project Name: Mountain Road Technology Park (the “Project”) Property: Hanover County (the “County”) Tax Parcels 7757-98-4106, 7767-08-0569, 7767-17-2423, 7757-97-5013, 7768-00-5491, 7757-96-5577, and 7757-96-1157 consisting of approximately
Full records for this county are part of a SitePath subscription.
State PSC dockets P1
No tracked activity yet — coverage expands weekly.
Local news P3
- 2026-10-06 Hanover Humane Society Says Data Center Noise Is Causing Dogs Pain Warehouse Plan Raises New Alarms
- 2026-08-16 Sunday Edition Electric Eyes
- 2026-08-06 Jefferson Lab Data Center Newport News
- 2026-06-24 Vcu Researcher Examines Air Quality Concerns Tied Virginia Data Centers
- 2026-05-19 Stack 100B Berry Hill Data Center Project
- 2026-05-12 The Data Centers Are Coming But Some Hanover And Henrico Residents Are Fighting To Stop Them
- 2026-05-06 Virginia Budget Stalled As Data Center Tax Fight Continues
- 2026-02-19 Following Goochlands Lead New Kent County Mulling Data Center Centric Tech Overlay District
- 2026-02-04 People Are Protesting Ai Data Centers And Its Scrambling Political Lines
- 2026-02-02 Why Data Center Development Is Moving To New Markets
- 2025-11-21 Proposed Data Center Incites Opposition From Hundreds Of Henrico Hanover Residents