SitePath › Local intel › Virginia › Halifax County
Virginia

Solar permitting — Halifax County, Virginia

FIPS 51083

On file: public meetings, local news, known opposition groups.

C
Halifax County, VA
Risk score 48/100 · Full scorecard →
Compliance: ModerateTrajectory: StableSaturation: Very High

Multiple large approvals; moderately supportive sentiment; setbacks (~200 ft); few denials noted. Permitting: SUP; 50-ft setback. Track record: denial on record — MORATORIUM then RESTRICTIONS: Halifax County supervisors i…

Permitting process

Local permitting pathway

SUP, CUP, SE

Setbacks & buffers

Halifax County-specific SE/SUP conditions control — county-set setbacks vary from 50 ft (rural) to 300+ ft (residential adjacent). Verify current Halifax County zoning ordinance for adopted local setback standards. — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.

Spacing requirements

Scenic corridor protections

Size restrictions

None codified; managed via CUP conditions

State-level permits & approvals

Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.

Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5

State incentive programs

Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.

Grid & interconnection

PJM / Dominion Energy Virginia (DEV) transmission zone

Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Battery storage (BESS) P1 State-Default Permitting

Standalone BESS (not co-located with approved solar): still requires county SE/SUP and host siting agreement

Local BESS ordinances & bylaws

County-level battery-storage status, safety requirements, and projects — each linked to a primary source.

Community opposition P1

Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.

SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to view

Energy-related meetings & dockets P1

solar · bess

Halo color matches the energy category tagged on each meeting.

  • 2025-05-05 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2024-12-17 Planning Commission
    Solar

    Halifax County must adopt a local solar ordinance by July 2026, consistent with a state-released model ordinance.

  • 2024-12-17 Other
    BESS

    Halifax County assesses revenue shares for solar photovoltaic projects and energy storage systems.

  • 2024-11-19 Planning Commission
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2024-10-07 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2024-08-20 Planning Commission
    Solar

    Supervisors discussed potential changes to the solar installation ordinance.

  • 2024-06-03 County Board
    Solar

    Halifax County Board of Supervisors will address the Conditional Use Permit application for Bluewave Solar's Opossum Branch project.

  • 2024-05-06 County Board
    Solar

    Councilor Long discussed the inconsistency in land use regulations for solar facilities compared to other outdoor recreation activities.

  • 2024-04-01 County Board
    Solar

    Sun Tribe Development presented the Aaron Creek Solar facility Conditional Use Permit for review.

  • 2023-11-21 County Board
    Solar

    South Boston G Solar Development submitted a Conditional Use Permit application for a new solar facility on Grubby Road.

  • 2023-04-03 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2023-03-06 County Board
    Solar

    Halifax County discussed a solar project and neighboring counties' actions on similar projects.

  • 2023-02-13 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2022-12-20 Planning Commission
    Solar

    Conditional Use Permit Application for an 80 MW Solar Facility on multiple properties

  • 2022-08-16 Planning Commission
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2022-04-19 Planning Commission
    BESS

    Halifax County assesses revenue shares for solar photovoltaic projects and energy storage systems.

  • 2021-11-16 Planning Commission
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2021-06-22 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • 2021-05-18 County Board
    Solar

    Halifax County Planning Commission to consider conditional use permit for 3.13 MW solar facility on Philpott Road

  • 2015-10-05 County Board
    Solar

    The solar project's acreage calculation was verified to be in accordance with the Ordinance.

  • County Board
    Solar

    Discussion of solar project benefits and contributions

  • County Board
    Solar

    Councilor Long discussed the inconsistency in land use regulations for solar facilities compared to other outdoor recreation activities.

  • County Board
    BESS

    County staff and Pine Gate Renewables negotiated a solar siting agreement

  • Planning Commission
    Solar

    The Planning Commission approved a special-use permit application for a 150 MW solar farm in agricultural district A-1.

  • Other
    Solar

    The Planning Commission approved a special-use permit application for a 150 MW solar farm in agricultural district A-1.

  • Zoning Board
    Solar

    Fees Zoning permits - $50 Conditional Use permits - $500 Large Scale Solar Conditional Use Permit - $1,000 Variances - $500 Plat Review - $25 ($5 for each additional parcel) Medical Variances - $25 (must be reviewed yearly) WebGIS WebGIS…

  • Other
    BESS

    Halifax County assesses revenue shares for solar photovoltaic projects and energy storage systems.

More energy-related meetings

Full records for this county are part of a SitePath subscription.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Local news P3

Explore every US county on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Virginia counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS. Last refreshed 2026-10-11. See the county risk scorecard or the full Virginia permitting index.