Solar permitting — Cumberland County, Virginia

FIPS 51049

On file: public meetings, PSC dockets, local news, known opposition groups.

C
Cumberland County, VA
Risk score 51/100 · Full scorecard →
Compliance: HighTrajectory: WorseningSaturation: Very High

Requires CUP; emphasizes non-farmland siting; very strong spacing rules (≥1 aerial mile from other projects); increasing resistance noted. Permitting: CUP; 50-ft setback. Track record: denial on record — Jamerson I…

Permitting process

Local permitting pathway

CUP, Conditional Use Permit, SE

Setbacks & buffers

100 ft from property lines; 500 ft from occupied dwellings

Spacing requirements

≥1 aerial mile from other solar projects and from villages per county policy (not formally codified in ordinance)

Size restrictions

None codified

Penalties & bonding

Total penalty: +5 (Denial +5)

State-level permits & approvals

Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.

Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5

State incentive programs

Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.

Grid & interconnection

PJM / Dominion Energy Virginia (DEV) transmission zone

Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Battery storage (BESS) P1 State-Default Permitting

Standalone BESS (not co-located with approved solar): still requires county SE/SUP and host siting agreement

Local BESS ordinances & bylaws

County-level battery-storage status, safety requirements, and projects — each linked to a primary source.

Community opposition P1

Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.

SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to view

Energy-related meetings & dockets P1

solar · bess · transmission

Halo color matches the energy category tagged on each meeting.

  • 2023-01-09 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2022-12-13 County Board
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2022-09-19 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2022-09-12 Other
    Solar

    Commissioners voted unanimously to approve a solar facility site

  • 2022-07-18 Other
    Solar

    Commissioners voted unanimously to approve a solar facility site

  • 2022-06-27 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2022-04-18 Planning Commission
    Solar

    Conditional Use Permit application for a Utility Scale Solar Facility was discussed.

  • 2021-11-15 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-09-20 Other
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-08-16 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-05-24 Planning Commission
    Solar

    Conditional Use Permit application for a Utility Scale Solar Facility was discussed.

  • 2021-04-13 County Board
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-04-12 Planning Commission
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-03-22 Other
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-03-09 Other
    Solar

    Johnson, Planning & Zoning Administrator RE: Further amendments to the Large-scale Solar Energy Ordinance 1 Proposed CA 21-05 Solar Facility Code Amendments Utility-scale solar energy facility shall be permitted with conditional use permit

  • 2021-03-09 Other
    BESS

    CUP 22-12 BOSTON HILL SOLAR PC Minutes 20220912 Page 2 of 5 CUP 22-13 Boston Hill Solar proposes a Solar Energy Project that will generate up to 115 MW AC with no battery storage, producing enough electricity to power up to 20,000 homes.

  • Other
    Transmission

    The transmission line project will interconnect with an existing overhead transmission line and carry generated electricity to the grid.

More energy-related meetings

Full records for this county are part of a SitePath subscription.

State PSC dockets P1

Local news P3

Explore every US county on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Virginia counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS. Last refreshed 2026-10-08. See the county risk scorecard or the full Virginia permitting index.