Standard SUP pathway; Western VA rural county adjacent to Roanoke metro; moderate siting friction. Permitting: A-1; 50-ft setback. Track record: Multiple CUP approvals 2019–2024. Political environment: Republican majority; key superv…
Permitting process
Local permitting pathway
A-1, Agricultural | SUP
Setbacks & buffers
Botetourt County-specific SE/SUP conditions control — county-set setbacks vary from 50 ft (rural) to 300+ ft (residential adjacent). Verify current Botetourt County zoning ordinance for adopted local setback standards. — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.
Spacing requirements
None codified
Size restrictions
None codified
Penalties & bonding
No penalties or adjustments. Standard CUP/SUP process.
State-level permits & approvals
Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.
Full records for this county are part of a SitePath subscription.
State policy & grid context
State RPS & clean energy policy
100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5
State incentive programs
Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.
Grid & interconnection
PJM / Dominion Energy Virginia (DEV) transmission zone
Full records for this county are part of a SitePath subscription.
Battery storage (BESS) P1 State-Default Permitting
Standalone BESS (not co-located with approved solar): still requires county SE/SUP and host siting agreement
Local BESS ordinances & bylaws
County-level battery-storage status, safety requirements, and projects — each linked to a primary source.
Community opposition P1
Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.
- Neighbors concerned about impact of Botetourt County wind farm Wind
- r/technology on Reddit: Virginia voter support for new data centers collapses from 69% in 2023 to 35% in new poll Data center
- r/Virginia on Reddit: Google struck a secret deal for 3 data centers in Botetourt. Public comment deadline is April 9th. Data center
- Two trends converge on Botetourt County: Data centers and solar farms. Data center
- Botetourt County faces opposition to data center, solar plans Data center
- Google reveals more details about Botetourt County data center plans Data center
- Protestors gather in Botetourt County, oppose data center Data center
SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.
Subscriber intel Subscribers
Researched for this county and available with a subscription:
- Project track record
- Developer intelligence
- Governing board
Energy-related meetings & dockets P1
Halo color matches the energy category tagged on each meeting.
- 2026-05-29 Planning CommissionData Center
The county discussed a data center project, addressing concerns about environmental impact and permitting.
- 2026-03-29 Planning CommissionSolar
The Planning Commission voted to approve a special-use permit for Barkett's Roanoke Road Solar 1, LLC c/o New Leaf Energy Inc.
- 2026-02-28 Planning CommissionTransmission
Pike Electric will lease a property for transmission line work and storm damage repair operations.
- 2026-02-09 OtherSolar
A proposed utility-scale solar facility on a 53-acre parcel south of Fincastle was discussed.
- 2026-01-29 Planning CommissionTransmission
Pike Fleet will stage vehicles for electric transmission and distribution services at this location.
- 2025-10-28 County BoardSolar
A resident expressed opposition to a proposed solar farm on Springwood Road due to environmental concerns.
- 2025-07-22 County BoardBESS
Awaiting plan resubmittal for the Gateway Grid Battery Storage project.
- 2025-01-28 County BoardBESS
Keri Martell supports Revenue Sharing in lieu of taxation for Battery Storage facility
- 2024-09-24 County BoardBESS
Consideration of advertising an ordinance for battery storage facilities in lieu of taxation
- 2024-07-23 County BoardSolar
Residents expressed opposition to a solar farm development in their area.
- 2024-03-26 County BoardWind
County officials discuss potential tax implications of idling wind turbines in a wind project.
- 2023-05-23 County BoardSolar
Proposed text amendments to the zoning ordinance to permit various types of solar energy facilities.
- 2023-05-08 OtherSolar
The Botetourt County Board of Supervisors proposes text amendments to the zoning ordinance to permit various types of solar energy facilities.
- 2023-01-24 County BoardWind
APEX Wind Farm plans are being reviewed and resubmitted in response to county comments.
- 2022-10-25 County BoardBESS
Authorization to review amendments to incorporate solar energy generating and battery storage facilities into the zoning ordinance.
- 2022-03-22 County BoardWind
Apex Clean Energy's wind project was criticized for lack of compliance with county requests for information.
- 2022-02-22 County BoardWind
APEX Wind Farm plats are currently under review.
- 2021-10-12 OtherWind
Discussion of natural resources required for a wind project
- 2021-06-22 OtherWind
Public hearing on the Rocky Forge wind farm project
- 2021-05-25 OtherBESS
Energy storage systems less than 150 megawatts are now considered partially taxable.
- 2021-01-26 OtherWind
Moriah Road in Eagle Rock stated that he is present to keep the Board informed of the Rocky Forge wind farm project.
- 2020-11-24 County BoardWind
Planning Commission discussed a wind farm project and expressed concerns about the permit approval process.
- 2018-06-05 OtherData Center
The Botetourt County Planning Commission voted to approve a data center project with SCC approval
- County BoardData Center
County discussed ongoing projects including data center expansion, vehicle purchases, and facility renovations.
- OtherData Center
Planning Commission voted to ask the Board of Supervisors to organize a public forum for the proposed Google data center campus
- OtherSolar
Botetourt County's zoning ordinance outlines differences between small solar systems and large commercial solar farms.
- OtherData Center
Planning Commission discussed the proposed infrastructure for a Google data center and confirmed the water authority's design standards.
- County BoardWind
APEX Wind Farm plans are awaiting resubmittal after fourth review comments were sent to Botetourt County.
- OtherData Center
The Botetourt County Board of Supervisors proposed a text amendment to the Zoning Ordinance to incorporate data center uses in the Research and Advanced Manufacturing Use District.
- OtherSolar
Botetourt County's zoning ordinance outlines differences between small solar systems and large commercial solar farms.
Full records for this county are part of a SitePath subscription.
State PSC dockets P1
No tracked activity yet — coverage expands weekly.
Local news P3
- 2026-09-28 Southwest Virginia Data Center Transparency Alliance Decries Lack Of Transparency Around Local Data Center Projects
- 2026-09-26 Why Real Name Behind Roanoke Countys Potential Data Center Matters
- 2026-09-25 High Energy Costs Data Centers Take Center Stage At Lt Governor Ghazala Hashmis Listening Tour Dominion Energy Nextera Energy Woodhaven…
- 2026-09-24 Data Center Spanberger
- 2026-09-23 Beth Macy On Proposed Roanoke Data Center Congress Must Get Involved
- 2026-09-23 Who Wants Buy Wood Haven Tech Park Digging Into Proposed Data Center
- 2026-09-10 Residents Rely On Freedom Of Information Act Requests To Fight Data Centers
- 2026-08-29 Grading Set Begin Google Data Center Campus Botetourt County
- 2026-08-28 Grading To Begin For Google Data Center Campus In Botetourt County
- 2026-08-21 Americans For Responsible Innovation On Data Centers Coming To Swva
- 2026-08-14 Data Centers Or Not Water Authority Is Planning For Future Expansion The Public Can Weigh In August 25
- 2026-08-13 Virginia Experts Concerned About Long Term Water Impact Google Data Center
- 2026-08-12 Local Experts Concerned About Long Term Water Impact Google Data Center
- 2026-07-22 Virginia residents line Route 220 over Google data center, demanding 'truth, transparency'
- 2026-07-13 Data Center Opponents Demand More Transparency During Rally Capitol Square
Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.