Solar permitting — Botetourt County, Virginia

FIPS 51023

On file: public meetings, local news, known opposition groups.

D
Botetourt County, VA
Risk score 61/100 · Full scorecard →
Compliance: ModerateTrajectory: StableSaturation: Moderate

Standard SUP pathway; Western VA rural county adjacent to Roanoke metro; moderate siting friction. Permitting: A-1; 50-ft setback. Track record: Multiple CUP approvals 2019–2024. Political environment: Republican majority; key superv…

Permitting process

Local permitting pathway

A-1, Agricultural | SUP

Setbacks & buffers

Botetourt County-specific SE/SUP conditions control — county-set setbacks vary from 50 ft (rural) to 300+ ft (residential adjacent). Verify current Botetourt County zoning ordinance for adopted local setback standards. — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.

Spacing requirements

None codified

Size restrictions

None codified

Penalties & bonding

No penalties or adjustments. Standard CUP/SUP process.

State-level permits & approvals

Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.

Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5

State incentive programs

Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.

Grid & interconnection

PJM / Dominion Energy Virginia (DEV) transmission zone

Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Battery storage (BESS) P1 State-Default Permitting

Standalone BESS (not co-located with approved solar): still requires county SE/SUP and host siting agreement

Local BESS ordinances & bylaws

County-level battery-storage status, safety requirements, and projects — each linked to a primary source.

Community opposition P1

Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.

SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to view

Energy-related meetings & dockets P1

wind · solar · data center · bess · transmission

Halo color matches the energy category tagged on each meeting.

  • 2026-02-09 Other
    Solar

    A proposed utility-scale solar facility on a 53-acre parcel south of Fincastle was discussed.

  • 2026-01-29 Planning Commission
    Transmission

    Pike Fleet will stage vehicles for electric transmission and distribution services at this location.

  • 2025-10-28 County Board
    Solar

    A resident expressed opposition to a proposed solar farm on Springwood Road due to environmental concerns.

  • 2025-07-22 County Board
    BESS

    Awaiting plan resubmittal for the Gateway Grid Battery Storage project.

  • 2025-01-28 County Board
    BESS

    Keri Martell supports Revenue Sharing in lieu of taxation for Battery Storage facility

  • 2024-09-24 County Board
    BESS

    Consideration of advertising an ordinance for battery storage facilities in lieu of taxation

  • 2024-07-23 County Board
    Solar

    Residents expressed opposition to a solar farm development in their area.

  • 2024-03-26 County Board
    Wind

    County officials discuss potential tax implications of idling wind turbines in a wind project.

  • 2023-05-23 County Board
    Solar

    Proposed text amendments to the zoning ordinance to permit various types of solar energy facilities.

  • 2023-05-08 Other
    Solar

    The Botetourt County Board of Supervisors proposes text amendments to the zoning ordinance to permit various types of solar energy facilities.

  • 2023-01-24 County Board
    Wind

    APEX Wind Farm plans are being reviewed and resubmitted in response to county comments.

  • 2022-10-25 County Board
    BESS

    Authorization to review amendments to incorporate solar energy generating and battery storage facilities into the zoning ordinance.

  • 2022-03-22 County Board
    Wind

    Apex Clean Energy's wind project was criticized for lack of compliance with county requests for information.

  • 2022-02-22 County Board
    Wind

    APEX Wind Farm plats are currently under review.

  • 2021-10-12 Other
    Wind

    Discussion of natural resources required for a wind project

  • 2021-06-22 Other
    Wind

    Public hearing on the Rocky Forge wind farm project

  • 2021-05-25 Other
    BESS

    Energy storage systems less than 150 megawatts are now considered partially taxable.

  • 2021-01-26 Other
    Wind

    Moriah Road in Eagle Rock stated that he is present to keep the Board informed of the Rocky Forge wind farm project.

  • 2020-11-24 County Board
    Wind

    Planning Commission discussed a wind farm project and expressed concerns about the permit approval process.

  • 2018-06-05 Other
    Data Center

    The Botetourt County Planning Commission voted to approve a data center project with SCC approval

  • County Board
    Data Center

    County discussed ongoing projects including data center expansion, vehicle purchases, and facility renovations.

  • Other
    Data Center

    Planning Commission voted to ask the Board of Supervisors to organize a public forum for the proposed Google data center campus

  • Other
    Solar

    Botetourt County's zoning ordinance outlines differences between small solar systems and large commercial solar farms.

  • Other
    Data Center

    Planning Commission discussed the proposed infrastructure for a Google data center and confirmed the water authority's design standards.

  • County Board
    Wind

    APEX Wind Farm plans are awaiting resubmittal after fourth review comments were sent to Botetourt County.

  • Other
    Data Center

    The Botetourt County Board of Supervisors proposed a text amendment to the Zoning Ordinance to incorporate data center uses in the Research and Advanced Manufacturing Use District.

  • Other
    Solar

    Botetourt County's zoning ordinance outlines differences between small solar systems and large commercial solar farms.

More energy-related meetings

Full records for this county are part of a SitePath subscription.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Local news P3

Explore every US county on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Virginia counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS. Last refreshed 2026-10-11. See the county risk scorecard or the full Virginia permitting index.