Solar permitting — Augusta County, Virginia

FIPS 51015

1 indexed meeting (1 energy-related), 2 news items.

D
Augusta County, VA
Risk score 57/100 · Full scorecard →
Compliance: ExtremeTrajectory: ImprovingSaturation: Very High

Most Restrictive Caps/Spacing. Permitting: SUP; 50-ft setback; hard 7,500-acre cap; extreme compliance stringency. Track record: denial on record — Multiple applications denied or withdrawn 2022–2024 after aggregate ca…

Key driver: Most Restrictive Caps/Spacing. Strict total cap (7,500 ac / 1,600 MW); severe 2-mile radius ban between projects; low max project size (≤200 ac).

Permitting process

Local permitting pathway

SUP, SE

Setbacks & buffers

Augusta County-specific SE/SUP conditions control — county-set setbacks vary from 50 ft (rural) to 300+ ft (residential adjacent). Verify current Augusta County zoning ordinance for adopted local setback standards.

Spacing requirements

≥2-mile radius ban between separate solar projects (2021/2023 amendments); prohibition zones in certain districts

Size restrictions

≤200 acres under panel per project (2021/2023 amendments)

Penalties & bonding

Total penalty: +15 (Denial +15)

State-level permits & approvals

Local permit: Special Use Permit (SUP) or Conditional Use Permit (CUP) in A-1 Agricultural zoning; issued by Board of Supervisors (BOS) or Planning Commission per county ordinance. Counties without zoning (Buchanan, Russell, Lee, Scott, etc.) proceed via revenue-sharing siting agreements. SCC CPCN: Va. Code §56-580 (as amended by HB 1558/SB 762, eff. Jul 2021) — SCC Certificate of Public Convenience & Necessity required for generating facilities ≥5 MW; waivable for utility-owned projects under SCC-approved IRP. DEQ Permit by Rule (PBR): Required for all solar facilities ≥1 MW per Va. Code §10.1-1197.6; includes VSMP/VPDES erosion & stormwater permits. Mar 2022 DEQ rule: solar panels counted as impervious surface same as parking lots. Revenue sharing: Va. Code §15.2-2288.7 — localities may require up to $1,400/MW-year for utility-scale solar on agricultural or forestal land; increases 10% in year 1 then every 5 years thereafter. VDACS notice: VA Dept. of Agriculture & Consumer Services must be notified for projects converting prime agricultural or forestal land. PENDING LEGISLATION (as of Mar 11, 2026): HB 711 (Herring) / SB 347 (VanValkenburg) both cleared both chambers and await Gov. Spanberger's signature (session ends Mar 14, 2026). If signed: (1) all localities must allow solar ≥1 MW via special exception — outright bans illegal; (2) statewide setback floor: 150–200 ft non-participating dwellings, 50–100 ft from state roads, 100–250 ft from streams/wetlands, 50–75 ft from property lines; (3) localities retain denial authority but must report reasons to SCC public database; (4) companion HB 891/SB 443: BESS permitted accessory use on approved solar SE sites. Spanberger is pro-solar; signature expected. Monitor: lis.virginia.gov.

🔒
Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

100% carbon-free by 2050 (Dominion), 2045 (APCo) | Virginia Clean Economy Act (2020) | Va. Code §56-585.5

State incentive programs

Virginia Clean Economy Act (VCEA, 2020): Dominion must reach 100% carbon-free by 2045; Appalachian Power by 2050; major driver of utility-scale solar procurement. Net metering: available under VCEA for systems up to 1 MW (by-right); large-scale behind-the-meter negotiated. SCC SolarShare: Dominion program offering renewable energy credits. Virtual net metering (Virginia): programs vary by utility. DEQ review: required for solar facilities ≥150 MW (permit by rule) or DEQ standalone review. Utility: Dominion Energy Virginia serves 2/3 of VA; Appalachian Power (AEP) serves western VA; Northern Virginia Electric Coop (NOVEC) serves NoVA exurbs; various rural cooperatives and municipal utilities.

Grid & interconnection

PJM / Dominion Energy Virginia (DEV) / Shenandoah Valley zone

🔒
Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Community opposition P1

No organized opposition on record for this county yet — no petition, group, or oppositional coverage tracked. Absence of opposition is a positive siting signal.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to viewSee plans

Energy-related meetings & dockets P1

1 meeting indexed for this jurisdiction; none flagged as discussing solar, BESS, data centers, wind, or transmission yet. Coverage expands weekly.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Local news P3

Explore all 3,143 counties on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Virginia counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS; sentiment derived from public meeting transcripts. Last refreshed 2026-07-12. See the county risk scorecard or the full Virginia permitting index.