SitePathLocal intelIndiana › Gibson County
Indiana

Solar permitting — Gibson County, Indiana

FIPS 18051

1 news item.

C
Gibson County, IN
Risk score 50/100 · Full scorecard →
Compliance: ModerateTrajectory: StableSaturation: High

Flat SW Indiana; Toyota manufacturing brings economic development mindset; SE pathway; limited track record. Permitting: Gibson County Area Plan Commission; 250-ft max / 40-ft min setbacks. Track record: Gibson Solar (NextEra Energy

Permitting process

Local permitting pathway

Gibson County Area Plan Commission (APC): CUP or Improvement Location Permit (ILP) in Agricultural district.

Setbacks & buffers

State default (IC 8-1-42): 50 ft from property line; 250 ft from dwelling; 40 ft from road; decommissioning bond required

Spacing requirements

None codified.

Size restrictions

None codified.

Penalties & bonding

No penalties or adjustments. Standard CUP/SUP process.

State-level permits & approvals

Local permit: Special Exception (SE) in A-1 Agricultural zoning via county Board of Zoning Appeals (BZA); some counties use two-step process (Plan Commission recommendation + BZA approval). BZA SE is the standard county-level pathway for all utility-scale solar. IURC CPCN: Indiana Code §8-1-8.5 — IURC Certificate of Public Convenience & Necessity (Cause No.) required for generating facilities >80 MW; process runs parallel to county BZA SE and does not replace it. IURC approval does NOT override a county BZA denial except where federal jurisdiction applies (see Mammoth Solar / Pulaski County precedent, 2023). IC 36-7-4: Indiana Code §36-7-4 limits how restrictive county ordinances can be for solar; basis for developer preemption litigation against overly restrictive ordinances (Randolph County 2024 litigation pending). SB 411 (2022): Voluntary 'solar-ready county' designation for counties meeting solar-friendly siting standards. SB 390 (2023): $1/MWh financial incentive for solar-ready counties.

🔒
Full permitting requirements

Full records for this county are part of a SitePath subscription.

State policy & grid context

State RPS & clean energy policy

No binding RPS — voluntary 10% by 2025 | Indiana Voluntary Clean Energy Portfolio Standard (2011) | Ind. Code §8-1-37

State incentive programs

Indiana Renewable Energy law (IURC): no Renewable Portfolio Standard — Indiana repealed its RPS (HB 1271, effective 2023). Net metering: available for ≤1 MW retail customer generation (IURC regulated utilities); Indiana Michigan Power (AEP), Duke Energy Indiana, Vectren/CenterPoint, NIPSCO offer programs. IURC CPCN: required for generating facilities ≥80 MW. HEA 1381 (2022): counties retain siting authority for solar in unincorporated areas. No state cash incentive program for solar. Utility: Duke Energy Indiana serves central/eastern IN; NIPSCO (NiSource) serves NW IN (Cook/Lake/Porter); Indiana Michigan Power (AEP) serves northeastern IN; Vectren/CenterPoint serves SW IN; REMC cooperatives serve rural areas.

Grid & interconnection

PJM / AEP Indiana Michigan Power (eastern IN border zone) — verify by exact project location

🔒
Full state policy & grid detail

Full records for this county are part of a SitePath subscription.

Community opposition P1

No organized opposition on record for this county yet — no petition, group, or oppositional coverage tracked. Absence of opposition is a positive siting signal.

Subscriber intel Subscribers

Researched for this county and available with a subscription:

Sign in to viewSee plans

Energy-related meetings & dockets P1

No tracked activity yet — coverage expands weekly.

State PSC dockets P1

No tracked activity yet — coverage expands weekly.

Local news P3

Explore all 3,143 counties on the interactive map

Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.

Open the county map → SitePath home All Indiana counties
Data sources: public agendas/minutes from local government sites; PSC dockets from state regulators; news from GDELT and curated RSS; sentiment derived from public meeting transcripts. Last refreshed 2026-07-12. See the county risk scorecard or the full Indiana permitting index.