The data-center backlash hits PJM: four New Jersey towns move to ban or freeze data centers, with York County (SC) and Wilson County (TN) close behind
A coordinated wave of local data-center restrictions surfaced in SitePath's news layer this cycle. The trigger headline (GovTech, 2026-06-22, in SitePath's news index) was "Data Center Bans Emerge in 4 More New Jersey Communities." The…
What changed
A coordinated wave of local data-center restrictions surfaced in SitePath's news layer this cycle. The trigger headline (GovTech, 2026-06-22, in SitePath's news index) was "Data Center Bans Emerge in 4 More New Jersey Communities." The meeting-researcher pass identified and sourced the four municipalities to primary records — and the picture is sharper than the headline:
- Warren Township (Somerset Co.) — permanent ban, adopted. Ordinance 26-19 designates data centers a prohibited use in all zoning districts, given final adoption 5–0 on 2026-06-18. Confirmed against the township's own adopted-ordinance PDF (confidence 0.90).
- Red Bank (Monmouth Co.) — binding ban, adopted 2026-06-11, unanimous: a zoning ordinance amendment to Chapter 490 prohibiting data centers as a permitted use in all zones, plus a separate "AI Accountability" resolution urging a statewide pause. Red Bank was the first NJ town to call for a statewide moratorium (confidence 0.82; ordinance number still to confirm).
- Asbury Park (Monmouth Co.) — Resolution 2026-264, adopted unanimously 2026-06-10. Note: this is a policy resolution — a local hold on data-center applications/zoning changes pending a code amendment, plus a statewide-moratorium call to Governor Sherrill — not yet a binding zoning ban (confidence 0.88–0.92).
- Sayreville (Middlesex Co.) — 18-month moratorium (Ordinance 15-26) introduced on 2026-06-15; a motion to substitute a permanent ban failed 3–3 on the mayor's tiebreaker. Not yet law — public hearing/final adoption set for 2026-07-20 (confidence 0.88). (The two source passes disagree on the introduction vote — 5–0 vs 5–1; confirm against the agenda.)
All four sit in PJM; Warren Township is confirmed in PSE&G electric territory, the others in JCP&L (FirstEnergy) — still PJM load. The GovTech "bans" framing is loose: only Warren and Red Bank are enacted bans; Asbury Park is a resolution and Sayreville is a moratorium not yet adopted.
Two more counties outside NJ are on the same track:
- York County, SC (FIPS 45091) — a nine-month moratorium on data centers in unincorporated York County passed first reading 2026-06-15/16 (sources differ by a day; Councilmember Roddey abstained pending legal advice on the QTS facility under construction off Hans Mill Hwy, whose vested-rights status is uncertain). Second reading June 29; final reading July 13. The $1.5B project advanced at the same meeting is not a data center — it is "Project Palmetto Rock," an unnamed global biopharma proposing a ~$1.49B HQ + manufacturing plant (1,252 jobs) at Palmetto Research Park in Rock Hill, with a $65M state grant — exempt from the moratorium (confidence 0.85–0.92).
- Wilson County, TN (FIPS 47189) — the Planning & Zoning Committee advanced a six-month moratorium 2026-06-22 (scoped to C4 commercial zones), creating a six-member study committee to write defensible rules; the county attorney flagged that it may not survive a court challenge. Full County Commission vote is 2026-07-20 — not yet in effect (confidence 0.78).
Why it matters
New Jersey is a PJM state. A four-town wave there — two outright bans already on the books, one local freeze, one 18-month moratorium pending — is the clearest sign yet that the Virginia-style data-center siting backlash is now a region-wide PJM phenomenon, not a Virginia exception. The pattern is also explicitly statewide-minded: Asbury Park and Red Bank didn't just protect their own borders, they passed resolutions pressing Trenton (and Governor Sherrill) for a statewide moratorium. SitePath's own SitePath's data-center dataset already carries a state-rollup note that a NJ data-center bill "passed both chambers (Assembly 55-18), awaits Governor Sherrill signature" — consistent with, but not yet confirmation of, a statewide measure.
The opposition is load-specific, not anti-growth. York County, SC froze data centers in the same session it advanced a $1.5B biopharmaceutical project — a county sorting large loads by water draw, power demand, and tax terms rather than rejecting industry. That is the same calculus driving Virginia's data-center politics, and it travels.
For the dataset, this is a freshness gap to close. The curated SitePath's data-center dataset has not caught up: the relevant NJ counties still read status: "No Specific Activity", York County (SC) still reads "No confirmed county-specific data center ordinance" (lastActionDate 2025-11-10), and Wilson County (TN) is absent from the counties array. The tracked counters (moratoriumActive 22, banEnacted 1, townshipMoratorium 10) were unchanged day-over-day. The news and meeting layers are ahead of the structured layer — these confirmed actions should be promoted into the county records and counters (Warren Township alone is a clean new banEnacted).
Recommended next steps (human)
- Promote the confirmed actions into SitePath's data-center dataset county records and increment counters — Warren Township →
banEnacted, Red Bank → ban, Asbury Park/Sayreville → moratorium/township-moratorium, York SC + Wilson TN → proposed/active per stage. - Resolve NJ jurisdiction tagging to the municipal level (records currently sit at county FIPS).
- Confirm the NJ statewide bill status before any "state permitting rule change" claim is made publicly.
- Calendar the 2026-07-20 Sayreville and Wilson County votes and the York County July 13 final hearing for follow-up.
Published from the SitePath editorial desk on June 28, 2026. Claims are traced to primary documents and to records already in the SitePath dataset; source links appear inline. Material the source review could not confirm has been withheld from this page rather than published with a caveat — see methodology for how SitePath sources and scores what it publishes.