Solar permitting — Fannin County, Texas
On file: local news, known opposition groups.
No active county solar moratorium (adjudicated 2026-09-08). Permitting: no county zoning — solar is by-right in unincorporated areas. Track record: Phoenix Solar (Pattern Energy) — 105 MW / 83 MWac; OPERATIONAL; Digital Realty 12-year PPA; 200 construction…
Key driver: Grade B: No solar ordinance, no solar moratorium. Two large operational projects (Phoenix 105 MW + Coniglio 168 MWp). However wind moratorium discussions (Apr 2024) indicate some board willingness to restrict renewables — monitor for spillover to solar ordinance. SPP territory (different grid than most TX counties). Current trajectory: Stable.
Permitting process
Local permitting pathway
No ordinance — by-right in unincorporated areas for solar.
Setbacks & buffers
None codified — no county zoning in unincorporated Texas counties. Texas Local Government Code limits county zoning authority. Cities may set setbacks within ETJs. — NOTE: the distances above are a STATE-level fallback, not a figure read from this county's own ordinance. We hold siting-rule records for this county which may include a stricter local limit we have not yet extracted. Verify against the county's own ordinance before relying on these.
Spacing requirements
None codified — no county zoning. No inter-project spacing requirements in unincorporated Texas.
Size restrictions
None codified; managed via CUP/SUP conditions
State-level permits & approvals
No state siting board for solar in Texas. PUCT regulates utilities; ERCOT manages interconnection for ERCOT service territory (most of state); SPP governs Panhandle/northwest TX. County Commissioners Court governs unincorporated areas under Texas Local Government Code. Many rural TX counties have NO zoning authority — solar is essentially by-right without county approval requirement. HB 2527 (2023) requires counties with solar ordinances to provide a 'reasonable' permitting framework. No statewide preemption prevents county restrictions. ERCOT interconnection queue is severely congested — grid study delays of 2-4+ years common.
Full records for this county are part of a SitePath subscription.
State policy & grid context
State RPS & clean energy policy
5,880 MW by 2015 (reached 2009) | Senate Bill 7 (1999) — capacity-based RPS | PURA §39.904
State incentive programs
Texas has no state RPS mandate. Key incentives: Federal ITC (30% base + bonus adders for energy communities/domestic content). Property tax abatement via Chapter 312/313 successor frameworks (county-level negotiation required). ERCOT wholesale market provides strong merchant revenue stack. No state income tax benefits developer HQ decisions. USDA REAP available for rural projects.
Grid & interconnection
SPP (Southwest Power Pool) — Northeast Texas
Full records for this county are part of a SitePath subscription.
Battery storage (BESS) P1 State-Default Permitting
No confirmed county BESS ordinance
BESS ordinances & bylaws
County-level battery-storage status, safety requirements, and projects — each linked to a primary source.
Community opposition P1
Organized opposition signals on record for this county — petitions, community groups, and oppositional coverage — each linked to its primary source.
- Fannin Co. residents urge commissioners to take action against wind turbines Wind
- Fannin County Commissioners Court discusses moratorium on wind farms Storage
SitePath maintains the most complete community-opposition dataset available, refreshed continuously from primary sources.
Subscriber intel Subscribers
Researched for this county and available with a subscription:
- Project track record
- Developer intelligence
- Governing board
Energy-related meetings & dockets P1
No tracked activity yet — coverage expands weekly.
State PSC dockets P1
No tracked activity yet — coverage expands weekly.
Local news P3
Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.