Solar permitting — Merced County, California
8 indexed meetings (8 energy-related), 5 news items.
Active San Joaquin Valley solar + BESS county with flat, fallowed agricultural land and a deep pipeline (operating: Wright 200 MW, Quinto 108 MW, Vega 20 MW; approved 2024–26: Zeta 75 MW+BESS, Las Camas 200 MW; in progress: Spikes Peak 150 MW+150 MW BESS, Cougar ~200–252 MW BESS, Gonzaga Ridge wind repowering). Permitting: Conditional Use Permit under Title 18 Zoning Code for off-site "Energy Generation Facilities"; ground-mount solar setback is height-proportional (≥100% of structure height, §18.30.030(C)(2)(m)) — no fixed-footage cap. County practice: project-specific General Plan Amendment + Solar Overlay Zone + Solar Benefits Agreement, CEQA EIR, Planning Commission decision (10-day appeal). No standalone BESS or data-center ordinance and no moratorium. Political environment: 5-member nonpartisan Board (2026 Chair Daron McDaniel); every major project on record approved; opposition low and reactive. Grid: CAISO — PG&E. Developer verdict: proceed on the standard CUP pathway; for Williamson-Act land plan a Notice of Non-renewal (no new WA contracts since 2009) and confirm current conditions with the Planning Division before executing land agreements.
Key driver: Active San Joaquin Valley solar development county with flat agricultural land and growing pipeline; former Castle Air Force Base provides additional siting opportunities on non-agricultural land; PG&E transmission accessible; UC Merced campus driving population growth and some land competition; Williamson Act land removal proceeding on lower-quality soils; dairy industry proximity rules add some complexity; solid B-grade development environment
Permitting process
Local permitting pathway
Conditional Use Permit (CUP) for off-site/grid-export "Energy Generation Facilities" under Title 18 Zoning Code (Ch. 18.10 Table 2-1; CUP procedures Ch. 18.116); CEQA review (full EIR typical for utility-scale). County practice pairs a project-specific General Plan Amendment + Solar Overlay Zone + negotiated Solar Benefits Agreement. Decision by Planning Commission (appealable within 10 days). Williamson Act land: Notice of Non-renewal (9-yr) or cancellation; county has not accepted new WA contracts since 2009.
Setbacks & buffers
Ground-mounted solar: setback from all property lines and habitable structures at least 100% of structure height (height-proportional), per Zoning Code §18.30.030(C)(2)(m). No fixed-footage utility-scale solar setback is codified; project-specific conditions are set through the CUP.
Spacing requirements
None specified
Size restrictions
Off-site/grid-export solar and co-located BESS require a CUP; on-site-use energy generation is permitted by right. No county acreage cap; decommissioning handled case-by-case as a CUP condition (e.g. Zeta Solar $4.46M decommissioning plan).
Penalties & bonding
No penalties or adjustments. Standard CUP/SUP process.
State-level permits & approvals
County zoning + CEQA review required; CEC siting jurisdiction for projects >50 MW on state/federal land; Coastal Commission review for coastal zone; DRECP DFAs streamline desert county permitting
Full records for this county are part of a SitePath subscription.
State policy & grid context
State RPS & clean energy policy
60% by 2030, 100% zero-carbon by 2045 | SB 100 (2018) + SB 1020 (2022) | Pub. Util. Code §399.11 et seq.
State incentive programs
Federal ITC eligible; California Self-Generation Incentive Program (SGIP) for storage; CA Renewables Portfolio Standard procurement; CPUC approved procurement programs
Grid & interconnection
CAISO — PG&E Balancing Authority
Full records for this county are part of a SitePath subscription.
Battery storage (BESS) P1 State-Default Permitting
No confirmed standalone county BESS ordinance — except: San Diego County (100 ft setback from residential/institutional/educational); Los Angeles County (10 ft setback from property lines and building
Local BESS ordinances & bylaws
Tracked storage projects
Full records for this county are part of a SitePath subscription.
County-level battery-storage status, safety requirements, and projects — each linked to a primary source.
Community opposition P1
No organized opposition on record for this county yet — no petition, group, or oppositional coverage tracked. Absence of opposition is a positive siting signal.
Subscriber intel Subscribers
Researched for this county and available with a subscription:
- 🔒Project track record
- 🔒Developer intelligence
- 🔒Community & board sentiment
- 🔒Governing board
Energy-related meetings & dockets P1
Halo color = sentiment of the relevant agenda excerpt: green positive, yellow neutral, red negative.
- 2026-02-10 Board Of SupervisorsSolar
Board of Supervisors approved a 160-acre expansion for the Las Camas Solar Overlay
- 2026-01-28 Planning CommissionSolar
Planning Commission heard the Las Camas Solar ~160-acre expansion (GPA25-003/ZC25-003/CUP25-016) and recommended approval to the Board; PC minutes not yet posted (outcome inferred from the Feb 10 2026 Board approval).
- 2026-01-14 Planning CommissionSolar
Las Camas Solar expansion item was continued to a future meeting.
- 2025-04-08 Board Of SupervisorsBESS
Board of Supervisors approved and authorized the Solar Benefits Agreement for the Zeta Solar + BESS Project.
- 2025-03-19 City CouncilBESS
Los Banos resident raised fire-safety concerns about a nearby battery storage project and requested a preparedness briefing.
- 2025-03-11 Board Of SupervisorsSolar
Board of Supervisors certified and approved a solar project with a capacity of 200 MW.
- 2025-02-26 Planning CommissionBESS
Planning Commission approved a battery storage project with 75 MW PV and 600 MWh BESS south of Los Banos.
- 2024-12-04 Planning CommissionSolar
Planning Commission recommended approval of a 200 MW solar project.
Full records for this county are part of a SitePath subscription.
State PSC dockets P1
No tracked activity yet — coverage expands weekly.
Sentiment rollup P2
No sentiment rollup yet (requires meeting transcripts to be processed).
Local news P3
- 2026-05-20 Tid Canals Install Solar Panels Concept Could Spread Across State
- 2026-05-16 Water Power Combination
- 2025-03-05 Proposed Merced County solar and battery project faces resistance amid environmental concerns
Filter by grade, state, moratorium status, and compliance stringency. Compare counties side by side.